View Full Version : Transpotable database without previous versions of model network



Jonckheere BVBA
November 12, 2015, 06:47 AM
Is it possible to make a transportable database with just the most recent version of the model network? (InfoWorks ICM 6.0)

When making a new transportable database I copy the runs and paste them in the new transportable database. The model network used in the runs are automatically pasted in the transportable database.
This pasted model network still contains all the previous versions that weren't used in the runs.
Even when the network version is branched, the original model is also copied and pasted (picture).
182

Is it possible to make a transportable database with only the branched network?

Duncan Kitts
November 19, 2015, 08:44 AM
Hi, This is now possible in 6.5. It is possible to take the latest network in version 6, if you create a scenario and then duplicate the scenario. This will provide a new network with no history. Of course you would then have to rerun the simulations.